Various Closures on Route 51 and Route B in Butler and Stoddard County for Bridge Repairs
 Route 51 and Route B between Fisk and Poplar Bluff, Mo., will have various closures as contractor crews perform bridge repairs. The crew will be working on a total of 10 bridges located between US 60 and Business 60.  

Improvements are already underway from Route 60 Outer Road to Route FF in Fisk, Mo. The repairs in this location are expected to be completed Oct. 23, weather permitting.

Crews will progress from east to west, with each bridge remaining closed for several weeks as repairs are underway.

Completion of the 10 bridges is anticipated in March 2018, weather permitting.

The work zone will have message boards and signs in place. Motorists are urged to use extreme caution while traveling near the area.

Route 51 and Route B between Fisk and Poplar Bluff, Mo., will have various closures as contractor crews perform bridge repairs. The crew will be working on a total of 10 bridges located between US 60 and Business 60.  

Improvements are already underway from Route 60 Outer Road to Route FF in Fisk, Mo. The repairs in this location are expected to be completed Oct. 23, weather permitting.

Crews will progress from east to west, with each bridge remaining closed for several weeks as repairs are underway.

Completion of the 10 bridges is anticipated in March 2018, weather permitting.

The work zone will have message boards and signs in place. Motorists are urged to use extreme caution while traveling near the area.

Last Updated on October 17th 2017 by Dee Loflin